Days 117-121

Things start to slow down a little now with the house build as the work involved takes more time.

This week the gyp rock went up onto the walls.  It took the guys all week to do this as pretty much every surface has to be covered.  All the walls, ceilings, cupboards, stairways – everything except the floors.  The gyp rock first went up in the places where the air conditioning units were to be located.  This meant that these could be put in without having to wait for the rest of the house to be covered.

It was great to see the rooms appearing as the framing was covered.  They seemed to be larger now they were a closed in space.